San Mateo Bridge Work Crews Beat the Clock

Early completion of seismic upgrades over the weekend means bridge won't close later this week as previously planned. The bridge was expected to reopen by 5 a.m. today.

Caltrans officials announced on Sunday that the San Mateo-Hayward Bridge will not have to be closed next weekend because earthquake safety work on the bridge is ahead of schedule.

The bridge shut down on Friday night so crews could install a new seismic joint and replace 60 feet of the bridge deck just east of the high rise, officials said.

The deck replacement work was farther along than anticipated after Saturday, so Caltrans said another planned closure on Oct. 26-29 will not be necessary.

Find out what's happening in San Mateowith free, real-time updates from Patch.

The bridge was expected to reopen by 5 a.m.

Suggested alternate routes for motorists during any closures are the Dumbarton Bridge, the Bay Bridge or a southern route along state Highway 237.

Find out what's happening in San Mateowith free, real-time updates from Patch.

The project costs $3 million and is being funded by the Bay Area Toll Authority.

 

- Bay City News

 